Maamba Collieries Limited (MEL) Extract from 2023 Annual Report

In 2023, significant developments were observed at Maamba Collieries Ltd (MCL), particularly around the Maamba Power Station and its coal mining operations. MCL operates a modern Coal Handling and Processing Plant (CHPP) that facilitates the production of different coal products with consistent quality. Since its privatization in 2010, MCL has made significant improvements in managing coal dumps to mitigate air pollution caused by spontaneous combustion in the overburden dumps. These efforts in environmental management have been recognized through awards from the Zambia Environmental Management Agency (ZEMA) .  

Maamba Collieries Limited (MCL) reported total revenue of ZMW5.00 billion (US$243.69 million) for the year ended 31 December 2023 (2022: ZMW4.75 billion (US$278.68 million)) and had a profit after tax of ZMW2.57 billion (US$125.04 million) (2022: profit of ZMW1.53 billion (US$89.95 million).  

In 2022, ZESCO, Zambia’s state power utility, reached a settlement in international arbitration with Maamba Collieries Ltd to pay $518 million by August 2024 to settle outstanding arrears for power supplied. This settlement follows arbitration in London where both parties agreed on the terms for resolving the debt. According to the agreement, ZESCO will discharge the arrears in tranches by August 2023, after adjusting for a cash discount of $60 million extended by Maamba. The settlement was reached amicably to address overdue power purchase bills while ensuring that monthly payments for power sales from May 2022 are fully paid to Maamba. As at the year ended 31 December 2023 the outstanding debt from ZESCO to Maamba was USD323.18 million (2022:US$539.93 million).  

The Maamba Power Station, fuelled by low-grade coal from MCL’s Maamba mine, plays a crucial role in Zambia’s energy sector. Currently, the station has two operating units, each with a capacity of 150 MW, commissioned in 2016. There is potential for expansion, with plans to add two more units, each also with a capacity of 150 MW, to meet the growing electricity demand in the country. This expansion, projected to cost around US$400 million, would potentially double the station’s output to 600 MW.  

Maamba Collieries has also explored the possibility of increasing the power station’s capacity to 600 MW to support Zambia’s ambition to become an electricity hub in the region. A technical feasibility study for the expansion was completed, and MCL is seeking third party funding for the project. These developments indicate MCL’s commitment to enhancing energy production capabilities in Zambia, contributing significantly to the national grid and supporting sustainable energy security in the region.  

During the year, Maamba undertook semi-annual maintenance on unit 1 of the 150 MW thermal power units between 4th August 2023 to 17th August 2023. Unit 2 underwent semi-annual maintenance between 25th March 2023 and 7th April 2023 as well as forced shut  